Hi All,

I have created a process order and then also created a control recipe.

My question is after the control recipe is generated, if we change the components, batch etc in process order, how can we update the control recipe with these changes.

Regards,

Naren

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Good morning Friends,

Can some one please help me on this?

Regards,

Narendra

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please try this go to COR2--Function--Control Recipe you must delete the generated process instructions for all phases with the same control recipe destination. And regenerate same after that.

For that, the order have to received a process message go to

Transaction : CO57

Process Msg: PI_CRST

and Discarded same,

Send this message and you can create a new control recipe again.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hello Mr. Brahmankar,

Many thanks for the reply.

The process which you have mentioned can be followed only if the status of the PI sheet is NEW.

In my scenario, my PI sheet process status in IN PROCESS and I have completed some steps in the PI sheet.

Now I add a new phase in the process order with all the details and I want this to be updated in the PI sheet, without affecting the data updated in PI sheet till now. How can this be achieved?

Regards,

Narendra

Former Member
0 Kudos

Hello Friends,

Can someone please revert to my query?

Regards,

Narendra

Former Member
0 Kudos

Hello Friends,

Can someone please revert to my query?

Regards,

Narendra

former_member184574
Active Contributor
0 Kudos

Hi,

This can not be done as already you have completed some steps in PI sheet.

Thanks

Vinamrath