Updated Requisition to automatically reflect on Purchase Order

troycollard
Newcomer
0 Likes
423

Is it possible to have a change/updated Requisition once re-approved to automatically reflect the updated changes on the associated Purchase Order?

Accepted Solutions (0)

Answers (1)

Answers (1)

BijayKumarBarik
SAP Champion
SAP Champion
0 Likes

Purchase requisition and purchase order tables are different(purchase requisition- EBAN and purchase order-EKKO & EKPO).

Purchase requisition created initially and then purchase order created which later send to vendor for delivery. In this case if you change Purchase requisition how the Purchase order needs to be changed as previous data of Purchase Order already sent to vendor! Better not to suggest business for your wanted concept to change PO once PR changes.

You can design if Purchase order is deleted the associated Purchase requisition can be deleted with development but not vice versa.