on 2008 Oct 23 9:02 AM
Dear gurus,
i have a requirement whit the delivery date = 30.12.08 , and a PO whit the delivery date = 19.7.09.
After the run Mrp the system create a new RP and the PO don't considered .
if I modify the delivery date in 19.6.09 the system planned the PO.
These days are approximately 200 , where i can modify the range for planned the PO whit the delivery date after 19.7.09?
Are this values the parameters correct for my requirement?
I try in customizing whit the transaction OPPQ , and in the material master of the material in the view MPR 3 but the don't planned the PO.
Thanks a lot for cooperation .
Daniele Pistilli
PP TEAM
Check the planning horizon with respective and MRP group wise in t.code OMDX
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use tcode OPPQ, select rescheduling horizon. Change the rescheduling horizon days to max and check it. Now system will consider planned order.
If you assigned MRP group in material master, do changes in OPPR, it is higher priority.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
9 | |
7 | |
5 | |
4 | |
4 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.