2024 Jul 30 5:12 AM - edited 2024 Jul 30 5:13 AM
I have a trigger point set up for operation 0250 on a specific routing, and it is working properly. Here's the situation:
- Production order quantity: 250
- Yield: 240
- Scrap: 0
- Rework: 10
Upon confirmation of the production order in CO11N, a rework order is generated for rework. However, when I start the confirmation for the first operation with 10 pieces as part of rework, the second operation does not show the quantity as automatic (the first operation is confirm type by Final confirmation).
Could you please guide me on how to solve this problem?
Request clarification before answering.