Dear Experts

I am getting below error message at time of Creation Of PIR through MD61 transaction.

Error message is

(Please enter valid requirements type).

Regards

SandeepPatil

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You need to run MRP

MD01 : Total Planning (All materials will be considered)

MD02 : Singl Item Multi level (Specified Material will be planned)

Planned order will be generated.

Regards,

Chintan

Answers (5)

Answers (5)

former_member539472
Contributor
0 Kudos

Which type of production you are doing ??

Please check with the of Requirement types.

IN MD61 one button is there USER PARAMETERS click on it .

Enter Requirements type in it.

BSF Gross planned indep. reqmts

LSF Make-to-stock production

VSE Planning w/o final assembly

VSEB Planning; phantom assemblies

VSEM Plng assemblies w/o final ass.

VSEV Planning the planning material

VSF Planning with final assembly

VSFB Planning for assemblies

and try with them. before that please check once the materail & plant cobinamtion with version.

And also check relevant setting in material master screen.

Former Member
0 Kudos

which type of production you are doing "make to stock" production??

please check with the of Requirement types

RqTy Requirements type description

BSF Gross planned indep. reqmts

LSF Make-to-stock production

VSE Planning w/o final assembly

VSEB Planning; phantom assemblies

VSEM Plng assemblies w/o final ass.

VSEV Planning the planning material

VSF Planning with final assembly

VSFB Planning for assemblies

and try with them. before that please check once the materail & plant cobinamtion with version.

Regards

S

Former Member
0 Kudos

Hi,

You might have not entered strategy for that material.

Enter strategy on MRP 3 view of material master .

You can enter make to stock strategy like 10,40 etc.

Regards,

Vishal

Former Member
0 Kudos

In MD61- Req parameters/User parameters screen , pls check the Req Type field .

Also check the strategy that you have maintained in the material Master MRP 3 view.

Former Member
0 Kudos

Dear Sheikh

Tnaks for your answer,whats the next step i have to do after Creating PIR to convert to production Order,Please guide.

Regards

Sandeep patil

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Sandeep,

Run MRP first in MD02, Single item Multi level then, go

in MD04 Double click on planned order it will give you option for convert planned order to production Order. Or you can also convert through CO40.

Regards

R.Brahmankar

islamibrahim
Participant
0 Kudos

Make sure to select the right strategy in the material MRP3 view for example use strategy 10 or 11 it should work (make to stock strategy)