Hello,
we would like to use time event confirmations for process orders with transaction CORZ.
Our master recipe has one operation with two phases:
On the calculation tab of the resource are six activities:
I assigned the recording type group "Processing" to the activities 3 and 4.
The recording type group "Setup" is also available. But it is not taken into account in transaction CORZ. So I didn´t assignt this recording type.
The activities 3 and 4 can be calculated automatically with time event confirmations.
Regarding the other acitivities I I would like to ask the following questions.
Thank you in advance.
Best regards
Julian