cancel
Showing results for 
Search instead for 
Did you mean: 

Time evaluation period is different from payroll period

4sarahabood
Newcomer
0 Kudos
240

Dear All,

We are working on +Ve time management but time evaluation period is different from payroll period.

The time period is 1 month before payroll period. So in month of October, the time results of September should be taken into consideration.

The issue is that according to business requirement, the customer wants to run time evaluation on a daily basis.

When this happens, the payroll reads the result of the current month along with the current month.

What’s the best solution for this case?

View Entire Topic
BGibbons
Active Contributor
0 Kudos

Hi,

Payroll uses function ZLIT to load time evaluation results into payroll. This function can take a PCR in Parameter 1. You can use this PCR to intercept results, interrogate their date and reject what you do not want to pass to payroll.

bg

OmarMohamed
Newcomer
0 Kudos

Hello

I just start implementing time evaluation and the time has different period it’s start from 17 to 16 next month and payroll from 01 to 30 

B2 cluster and ZL table just imported data only from 01 to 16 

can you help me how to make B2 and ZL imported as per time evaluation period from 17 to 16