Hi,

As far as I know there are three ways of extracting PR timestamps.

Opt 1. CDHDR-UDATE + CDHDR-UTIME

  • When PR is created manually, CDHDR contains items in OBJECTCLAS=BANF, OBJECTID=PR number padded, CHNGIND=I

Opt 2. EBAN-BADAT: Requisition (request) date

  • Specifies the date on which the purchase requisition was created. (cf. F1 Help)
  • Regardless of its origin, BADAT is given system date.

Opt 3. EBAN-CREATIONDATE + EBAN-CREATIONTIME

  • Purchasing Document Creation Date + Purchasing Document Creation Time
  • When PR is created manually, CREATIONDATE + CREATIONTIME is given system date, though we cannot see in tcode ME53N.

Here is the question.

  1. Are these all correct?
  2. What could be the difference between Opt. 1 and Opt. 3?
  3. Any idea to extract created "time" not through manual registration, such as MRP logs?

Thanks