This WBS element is already assigned to another sales document - error on Sales Order

Seb001
Explorer
0 Kudos
399

Hi SAP S/4HANA Cloud Public Edition Experts,

I am currently having some difficulties in assigning an Enterprise Project with Revenue to my sales order line items.

Once I select the project, I get the error "This WBS element is already assigned to another sales document" - this happens to other projects, not just one. However, in order to test this from scratch, I have recreated the project, making sure it's not sued on other sales orders.

Based on some KB articles and community posts, I understand that there are some setting I need to apply to the Project, some of those below:

1. Make sure the project profile is "Project with Revenue"

2. Multiple Sales Order Items Scenario "Yes"

3. Project Stock - is marked with "Yes" - even if this not an available selection

4. Billing Element - "Yes"

5. Budget Availability Control Profile - PS001

6. Budget Availability Control Active - "Yes"

7 Costing Sheet - 1110PI

After Releasing, I can select the project on the sales order lines. However, on save, I get the same error.

Can someone let me know what can be the issue here?

Regards,
Seb

 

 

 

 

Accepted Solutions (0)

Answers (1)

Answers (1)

SharanPadshetty
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Seb,

Kindly try the 2 options mentioned below,

1. Uncheck Multiple Sales Order Items Scenario and try to to assign the WBS/Project.
2. Kindly check Revenue Recognition Key must be in sync with WBS and Sales Order.

Regards,

Sharan Padshetty