on 2013 Jul 30 8:27 AM
Hi Everyone,
Till now we were using SAP 4.6c version in that while creating a Tasklist we used to enter the Purchase Order under the Operations of Tasklist,
when we are trying to give same Purchase in ECC6 then it is giving an error as
Document not an outline agreement (please enter outl. agreement)
Why is difference in 4.6c and ECC6, and how to rectify the error.
Thanks & Regards,
Rajesh
Rajesh,
What is the full message text including the message number?
Also have a look at OSS Note 1364820
PeteA