Hi,

I want to have RM requirement based on sales order w/o MRP and w/o planning. To achieve this I have gone through table IBIN but that is helpful for configurable materials only.

Discrete materials are not available in same table IBIN.

For the time being I am using CSK1 but that is separate transaction. If I would got tables for CSK1 than it will solve my problems.

Regards,

Rampreet Jaiswal

View Entire Topic
former_member242092
Active Participant
0 Kudos

Hi Sumeet,

Thanks for your response.

Tables and t-code which you have shared that is useful for discrete materials but in my case we are maintaining super BOM with thousand of components in each level. We are implementing VC module and BOM gets updated in sales order based on some selection condition.

My question is how and where to find this sales order BOM component.

Regards,

Rampreet Jaiswal