on ‎2023 Oct 06 9:09 AM
Could you please help me out that in which tables the Distributable budget and Assigned budget are flow in CJ31 ?
Request clarification before answering.
Hi Mojesh,
Budget line items are in the BPEG and BPEJ tables. But do not expect to get everything from the tables, as some of those figures are calculated in real-time. System will not update available budget for each and every posting into a table.
Regards,
Paulo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please refer to this blog for PS tables.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.