Table flow for CJ31

mojesh03
Explorer
0 Likes
2,325

Could you please help me out that in which tables the Distributable budget and Assigned budget are flow in CJ31 ?

Accepted Solutions (1)

Accepted Solutions (1)

Paulo_Vitoriano
Active Contributor
0 Likes

Hi Mojesh,

Budget line items are in the BPEG and BPEJ tables. But do not expect to get everything from the tables, as some of those figures are calculated in real-time. System will not update available budget for each and every posting into a table.

Regards,

Paulo

mojesh03
Explorer
0 Likes
Thanks Paulo

Answers (1)

Answers (1)

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Likes

Please refer to this blog for PS tables.