Hello All Experts, 

One question, currently for Network-Materials system is creating Reservation instead of PO. 

What settings/configuration I need to do or required, so that system will start creating PO and not Reservation. 

Business wants PO to be created for Network-Material. 

Expert's guidance will be appreciated. 

Thank you. 

Regards,

Tanuj K.  

 

View Entire Topic
Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

When you assign a component to a NWA you specify the Procurement Type which controls how the system reacts to this component.  It can create a reservation, PR, etc.

In configuration the Procurement Type is created in OPS8, it's under Project System, Material, Procurement.

The default procurement type is specified in the Network Profile.

Creating a PO directly is not an option, PS can only create PRs directly, you can automate the conversion from PR to PO through MM.