on 2025 Feb 08 3:33 PM
Hello All Experts,
One question, currently for Network-Materials system is creating Reservation instead of PO.
What settings/configuration I need to do or required, so that system will start creating PO and not Reservation.
Business wants PO to be created for Network-Material.
Expert's guidance will be appreciated.
Thank you.
Regards,
Tanuj K.
Request clarification before answering.
When you assign a component to a NWA you specify the Procurement Type which controls how the system reacts to this component. It can create a reservation, PR, etc.
In configuration the Procurement Type is created in OPS8, it's under Project System, Material, Procurement.
The default procurement type is specified in the Network Profile.
Creating a PO directly is not an option, PS can only create PRs directly, you can automate the conversion from PR to PO through MM.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
9 | |
7 | |
6 | |
4 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.