One question, currently for Network-Materials system is creating Reservation instead of PO.
What settings/configuration I need to do or required, so that system will start creating PO and not Reservation.
Business wants PO to be created for Network-Material.
Expert's guidance will be appreciated.
Thank you.
Regards,
Tanuj K.
Request clarification before answering.
When you assign a component to a NWA you specify the Procurement Type which controls how the system reacts to this component. It can create a reservation, PR, etc.
In configuration the Procurement Type is created in OPS8, it's under Project System, Material, Procurement.
The default procurement type is specified in the Network Profile.
Creating a PO directly is not an option, PS can only create PRs directly, you can automate the conversion from PR to PO through MM.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tanuj;
There is no configuration that makes the system create a PO instead of a purchase requisition. What you can do is automatically create the purchase order from the purchase requisition. In this case, seek assistance from the MM specialist.
Regards
Marcio Blos
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 33 | |
| 17 | |
| 14 | |
| 13 | |
| 9 | |
| 4 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.