Subcontracting lead time

0 Kudos
388

Dear community,

I have a very usual scenario of subcontracting with components to be provided to the subcontractor. I use MRP areas for my subcontractor.

In terms of planification, the system calculates the required component's quantity in the subcontractor MRP area and generates a Transfer Reservation from my plant to the subcontractor in case of shortage.

My issue is that I am unable to manage a lead time for this reservation.

Example: the Transfer Reservation is due for the 14th of February at the subcontractor site

The requirement at the plant level is due for 13th, just one day before.

Where does this 1 day come from?

BR

Gregory

View Entire Topic
former_member677038
Participant
0 Kudos

Hi Gregory, don't you have a processing time for purchases in customizing?