Hi,
What is the significance of Strategy Group & how the system follow or search the path for Desired strategy ?
What is the name of MRP Table.
Thnx in advance
Request clarification before answering.
Hi,
To make up a product we need some requirements in the form of demand.
This requirements are independent requirements and customer requirements
To create a demand Program the Demand Management uses PIRS and
Customer Requirements and we need to define a planning strategy
Planning strategy define the methods of production for planning and
manufacturing a product.Using these strategies we decide whether
production is triggered by sales orders or not ie MTS OR MTO
Requirements classes:
We need to define requirements class which contains control parameters
for planning and consuming the PIR and customer requirements.
This Requirements class is to be assigned to requirements type
By doing this we are indirectly assigning the control parameters to
strategy via Requirements type
This Requirements Type is to be assigned to strategy
Strategy should be assigned to strategy group
Strategy group is to be assigned to Material in Mrp 3 view or via MRP Group.
Preference will be given to strategy maintaine in MRP 3 View.
If no strategy is maintained here the system searches for the MRP Group
Regards,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pradeep,
The significance of strategy group is you can cumulate the related planning strategies in this upto 8 and maintain for one finished part. You cannot plan and passed requirements of a finished part without planning strategy and this will be technically controlled by MRP type in the planning run.
The first prefernce will be given to the plannign strategy maintained in the MRP3 view planning group...if this is not mantained then system checks the MRP group planning strategy.
If it is not maintained at both places the material will be planned from MRp type but the you will not get the requiements with proper requireement type.
The MRP related tables are:
MDKP Header Data for MRP Document
T460C Order/Purchase order types for planned order
RESB Reservation/dependent requirements
PLAF Planned order
T438M Control Parameter for MRP -Material Level-
PBIM Independent requirements for material
If helpful then rewards your points.
Regards
TAJUDDIN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi pradeep,
Strategy
The planning strategy represents a planning procedure for planning a material.
It is defined by one of the following:
<b>a requirements type from demand management
a requirements type from sales order management
a combination of both that makes sense</b>
The strategies available for creating the master plan can be seen in step "Define strategy".
Strategy group
You use the strategy group to group together all the valid planning strategies. Thus, more than one planning strategy can be allowed for a material.
<b>MRP TABLES</b>
MDKP MRP Document Header Data
MDTB MRP Table Structure (no data)
PLSC Planning Scenario (Long-term Planning)
MDFD MRP Firming Dates
MDVM Planning File Entries
S094 LIS -- Stock/Requirements Analysis
THNAX
Sunil Jawalkar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
6 | |
5 | |
4 | |
4 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.