Strategy group 63

Former Member
0 Kudos
218

Dear expert,

In Strategy group 63- planning through demand managment using t-code MD61 then in STO case planned order is genrated instead of purchase requisition at planning plant but planned order genrated at manufacturing plant .I put the procurment key F as well as i also mention the special procument key.

Please suggest me the right way.

Accepted Solutions (0)

Answers (1)

Answers (1)

DerekDing
Product and Topic Expert
Product and Topic Expert
0 Kudos

Strategy group 63 which used in the finished material or semi-finished material, and the sales order of material will consump the PIR of planing materials.

And for the purpose of the Strategy group 63 will control the lower level component should be purchasing or not before the SO created, so it should not used Procument type =F, thank you.