on 2020 Feb 06 12:55 PM


I created one strategy based maintenance plan with the following strategy 100hrs,200hrs,300hrs,400hrs,
I created one measuring pointer as a counter for one Equipment,
Then I created one measuring document for that measuring point with 50hrs,
After that, I scheduled that maintenance plan with start counter value 0 hrs, When I save that Maintenance Plan it triggers the order automatically. But my measuring document does not reach the strategy. It is the standard process? or I need to change the some setting?
Request clarification before answering.
Hi Tirupathi, Thanks for your valuable reply, I give 100% call value in Horizon field. Now it holds the order in IP10. I enter 100Hrs in measuring document after that only order created. Thanks for your contribution.
I have another one query also https://answers.sap.com/questions/12971528/what-is-the-correct-user-exit-for-to-activate-the.html?ch...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 29 | |
| 15 | |
| 15 | |
| 6 | |
| 5 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.