Strategy Based Maintenance Plan - Scheduling calls

vinoth_kumar47
Explorer
0 Kudos
464

I created one strategy based maintenance plan with the following strategy 100hrs,200hrs,300hrs,400hrs,

I created one measuring pointer as a counter for one Equipment,

Then I created one measuring document for that measuring point with 50hrs,

After that, I scheduled that maintenance plan with start counter value 0 hrs, When I save that Maintenance Plan it triggers the order automatically. But my measuring document does not reach the strategy. It is the standard process? or I need to change the some setting?

View Entire Topic
vinoth_kumar47
Explorer
0 Kudos

Hi Thirupathi, Thanks for your reply. My call horizon % is 0 only.

Former Member
0 Kudos

Call horizon percentage is to calculate the time for creating the next maintenance order or notification after the start or completion of maintenance plan (Example: If the duration of cycle is 100 days and the call horizon is 0%, the system creates an order immediately; 90% , the system creates the call after 90 days and so on)

So, try set the Horizon 80% or 90% and test again.