on 2020 Feb 06 12:55 PM


I created one strategy based maintenance plan with the following strategy 100hrs,200hrs,300hrs,400hrs,
I created one measuring pointer as a counter for one Equipment,
Then I created one measuring document for that measuring point with 50hrs,
After that, I scheduled that maintenance plan with start counter value 0 hrs, When I save that Maintenance Plan it triggers the order automatically. But my measuring document does not reach the strategy. It is the standard process? or I need to change the some setting?
Request clarification before answering.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Call horizon percentage is to calculate the time for creating the next maintenance order or notification after the start or completion of maintenance plan (Example: If the duration of cycle is 100 days and the call horizon is 0%, the system creates an order immediately; 90% , the system creates the call after 90 days and so on)
So, try set the Horizon 80% or 90% and test again.
| User | Count |
|---|---|
| 29 | |
| 14 | |
| 14 | |
| 6 | |
| 5 | |
| 5 | |
| 4 | |
| 4 | |
| 4 | |
| 3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.