on 2023 Apr 11 4:40 PM
Hello Experts,
When we create planned order using MD11 in S4 ( along with ePPDS system) and we do not want system to auto schedule the order while updating/creating the planned order in PPDS. if we change the control key in Production version of the respective material to stop auto scheduling of the planned orders, then such orders are not getting tagged under resource/work center maintained in recipe, hence the order is not visible in resource chart in detailed scheduling board.
can anybody help to identify if this is possible to restrict changes in the planned order dates with resource getting assigned to the order.
Thanks in advance.
Request clarification before answering.