We are bonding some of imported consignment in custom bonded warehouse. It is being ex-bonded whenever it is required in factory unit for consumption.

When we run MRP , system recognises only stock maintained in factory. We want stock maintained in bonded warehouse to consider in MRP run. This will give us proper clarity & will throw requireemnt only when it is required after considering stock at factory as well as stock in warehouse

Can we have resolution for the same

regards

AnandG

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

You can achieve this with creating "scope of planning" in OM0E or special procurement keys

[MRP multi plants|http://help.sap.com/saphelp_46c/helpdata/en/f4/7d2d4d44af11d182b40000e829fbfe/content.htm]

ajitkumar
Active Contributor
0 Kudos

create specail procurement key stock transfer with the bonded ware house as supplying plant. in this way your requirements in plant will get cumulated to the WH. just by making it a plant and maintaining mrp data may not work if your valuation area is plant.

tejyadav
Active Contributor
0 Kudos

Hi, If your bonded warehouse is maintained as a plant in the systen then, activate the plant parameters for MRP for this bonded warehouse, once done system will consider the stocks lying in bonded warehouse in MRP.

Former Member
0 Kudos

In addition to maintaining the MRP paramters for plant (warehouse) also maintain the mrp parameters for all those material masters for which you want MRP run.

regards