Hellow SAP Gurus,

Here i have 2 roh material for 1 finish material. E.g A is my finish material for that i required 1 Roh R1/R2 means either R1 or R2. here R2 is Alternative material for R1.Now if i have R1 of 10Qty & R2 is 0 stock So after MRP run for material A 10Qty is it poosible system select R1 not R2 because R1 is in stock?

regards

Accepted Solutions (1)

Accepted Solutions (1)

madlercm
Active Contributor
0 Kudos

Hi,

MRP without enhancement DI (discreet industries) doesn't provide for material interchangeability.

You can only have an alternative item determination in the production order during ATP check, meaning that if R1 is defined as an alternative item in the BOM to R2 (BOM of A, in which R2 is a component), then when you do ATP for the order, if there isn't enough stock of R2, it will swich to R1.