I'm looking for precise procedure for steps after material ledger was activated in existing manufacturing company.
I have read many SAP notes and other Q&A here in SAP community but still can find an answer on my concerns.
I have done all necessary configuration for activation.
Do I have correct sequency of next steps:
1. Set ML productive - CKMSTART
2. Change price determination CKMM from 2 to 3
3. Run CK40N
4. Shift ML period MMPV
5. Open FI period for Jan 2025
6. Run CKMLCP
Is this correct?