on 2020 Apr 16 10:46 AM
Hi,
in the SAP Learning Hub's section on "source lists" the exercise shows 2 vendors for 1 material being marked as "fixed". If the "fixed" indicator defines the preferred vendor, I do not understand what happens if you mark 2 vendors as fixed and MRP relevant. Can anybody explain the background? Thanks!
Request clarification before answering.
Dear projectandsourcingoffice,
in S4/HANA public cloud two or more fixed vendors are not possible
What I know from ECC in the past this was different. But normally the system searches the entries in the responsible table and find the first valid one, this is not according to any logic - it is the first possible one with the table keys.
Nevertheless if you want to procure from two or more vendors "fixed" and get your purchase requisition assigned to the fix vendors then i recommend using the quotation function - below attached.
Two vendors are assigned in source list
On quotation header for the material
On item level two different vendors we share the quantity two vendors if needed
Best regards Dennis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
15 | |
10 | |
8 | |
5 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.