Dear Experts,

I'm testing the SOP flow, IN S/4 but I can't get the RCCP to work in MC81 transacation.... in any way!

Current Settings:

1) I've activated the SOP for the Plant

activation-sop-for-plant.png

2) OPU4 with both active flags. Here i try before SelID : 03, and then SelID : 01 because routing of the materials are N type.

opu4.png

3) LTP flag active in Work Center Capacity

ltp-flag-in-wc.png

So I created a product group in MC84 with 2 materials : SOP1 e SOP2, both materials have the production versions checked and verified.

product-group-mc84.png

I create in MC35 RCCP Profile as you can see in the screen.

mc35-1.png

mc35-2.png

When i check RCP in MC81 I have message MA300.

mc81-error.jpg

In Capacity-Work Center I use the standard Processing Formula SAP006, if I try to schedule a Planned Order, Capacity Requirement it's ok.

I mantain lotsize in routing as in production versions.

Does anyone have any idea what's missing?

Thank you!

Accepted Solutions (0)

Answers (5)

Answers (5)

0 Kudos

Thank you Mr Brahmankar!

afer the implementation of the note, finally it's working!

Best Regards

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

If it is working then kindly close the question.

Thanks a lot.

Best Regards,

R.Brahmankar

0 Kudos

Thank you Mr. Brahamankar,

but I had already written in my first post that I had created the production versions and I had also tried with SELID : 01 in OPU4.

Anyway even removing the REM profile from MRP4 and from production versions doesn't change the situation...

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Please implement SAP note SAP note 2751881 and try it again.

Also check work center and routing data maiantain for capacity planning and scheduling.

Best Regards,

R.Brahmankar

0 Kudos

Hello Mr Caetano e Mr Brahmankar and thanks you for your response!

Yes, I just tried to create a CPR for single material with MC87.

Obviously the material has a correct and verified production version.

production-version.jpg

and the RCCP profile has been created for the individual material with MC35.

mc35-header-sop3.jpg

mc35-for-material-sop3.jpg

In MC87 I always have the message MA300

mc87.jpg

What more could be missing?

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Please follow the steps from useful wiki document

Rough-Cut Capacity Planning on SOP

You have created task list N routing and used for repetitive manufacturing.

S/4 has only one scheduling level "detailed scheduling" may be try by maintaining the Detailed scheduling for 01 in OPU4.

Best Regards,

R.Brahmankar

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Have you created production version for your material?

Please check SAP note 2751881 - Scheduling Fails Due to Missing Production Version

Best Regards,

R.Brahmankar

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Did you try to run RCCP for a single material, rather than for a Product Group?