cancel
Showing results for 
Search instead for 
Did you mean: 
Read only

SLED Change after testing

Former Member
0 Kudos
788

I have some chemicals subject to SLED. Once the expiry date is reached before scrapping, they are tested.

If test results supports and prove that these chemicals can be used further, there expiry life SLED is extended.

How to configure this scenario?

Accepted Solutions (1)

Accepted Solutions (1)

former_member433442
Active Contributor
0 Kudos

Hi,

You can change the SLED for a batch in MSC2N basic data view.

Regards,

prabu

Answers (2)

Answers (2)

former_member197616
Active Contributor
0 Kudos

if the material is QM managed, please create a inspection lot and do the usage decision after posting to Quality inspection stock type .system will extend the shelf life.

If the material is not QM related change the batch properties and provide the next inspection date.

Hedy1
Newcomer
0 Kudos
system will extend the shelf life?what should i do to realize this?
murugan_mgl
Active Contributor
0 Kudos

HI,

Go to MSC2N and enter today's date in production and press enter .If u have given the sled in general plant date in the material master,the system will automatically calculate the expiration date.

regards

murugan