Single Process Order for two semi-finish material with stock updation.

Former Member
0 Kudos
219

Dear All,

Kindly provide help on below mentioned requirement ASAP:

Requirement: I have two different-different semi finish material which have two different-different bill of material. Can we create single process order for both materials.

Example: Suppose 101 is a semi finish material which is in semi solid state and 102 is second material which is in solid state. First,I will produce 101 than after 14 days it will convert into 102.I need stock details for both 101 and 102 materials. Price will be same for both 101 and 102 material.

For the production of both material,I need to create only 1 process order.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Issue Resolved:

I have used "Co-product" concept and resolved the issue.

Exp: I have entered 101 material in BOM as a component of 102 material with minus quantity.

Kindly suggest me, if anyone is having better option for this issue.

Message was edited by: Krishnapal Singh Chundawat

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

I think you can map the process using 101 as an intramaterial. You can post a goods receipt of this material on stock, adding it with a negative sign on the BOM of 102. Then you will include it again with a positive sign and refer it on a subsequent operation. That way, you will be able to see it on stock. In this case, you will only create one BOM for material 102 with all the components.

BR
Caetano

Former Member
0 Kudos

Dear Caetano,

As per my knowledge,Intra material will not appear for GI/GR as INTRA material type has no purchasing and MRP views.I have tried but not able to release the process order because availability check is missing in INTRA material. Can you please tell me,how to resolve that error. So i can continue with my testing on solution which provided by you.