Shift timing error - Shift finish 02:00:00 is after start of next shift 02:00:00

ssaher412
Participant
0 Likes
863

Hello,

I have defined shift timings as follows , A2 06:00 to 16:00, B2 16:00 to 02:00 and C3 02:00 to 06:00.

Assigned them in shift sequence. When i try to assign it to capacity of the work centre it gives error "Shift finish 02:00:00 is after start of next shift 02:00:00".

My shift sequence is as - A2, B2 & C2.

Shift define :-

ssaher412_1-1710135125364.png

Shift sequence :-

ssaher412_0-1710135034396.png

Request you to share your thoughts on this problem .

Thanks & Regards,

Shubham

@rupesh_brahmankar @

Accepted Solutions (1)

Accepted Solutions (1)

arjuna_bandara
Active Participant

Hi,

This is because the shift definition B2 and C2 span across 2 days.

As per the standard only last shift is allowed to start on previous day and end on next day.

Please refer the note 3331809

shift definition like below would allow to use without an error.

S16:00:0016:00:00
S216:00:0023:59:59
S323:59:596:00:00
ssaher412
Participant
Thanks Arjuna, understood the issue.I have to configure as per your suggestion or have to make B2 as my last shift.