I have installed  SAP IDES ECC6.0 EHP3 on Windows 2008 R2 from SAP DVD:

Ihave;

* installed oracle 10.2.0.4

* upgraded oracle to 10.2.0.5 version

* executed sapinst

* desactivated archivelog with BRTOOLS

* reboot server

* executed SGEN (client 001 , user DDIC)

SGEN is very slowly (about 1 object by minute....).

When I am looking for job every thing is OK and 8 process are started.

When I am looking on server with task manager I saw that all CPU time is used with oracle.ex and nearly nothing with disp+work.exe.

Remark: I made and other installation (exatcly the same) BUT WITHOUT REBOOT server) and SGEN finished about 1 day....

Many thanks for your ideas.....

Regards.

C.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Charlotte!

Try to update SAP kernel to the latest version and repeat generation after that.

Also check that free space is enough in oracle tablespaces.

Best Regards,

Aleh

Answers (2)

Answers (2)

0 Kudos

Hi Charlotte Bragard,

Please check the following SAP Notes -

1002815  SGEN Performance Issue

1132507  SGEN: Using maximum number of free work processes

379918    Redesign of the SGEN transaction

406974    Scheduling new SGEN in the background

162991    Generation tools for ABAP programs

438038    Automatic regeneration of invalidated loads

589124    Performance improvements when Support Package imported

Hope these help.

Regards,

Sriram

0 Kudos

Hi Aleh,

Thanks for your anwer

I had already upgrade kernel (level 333).

For Oracle I have looked for all logs but not saw tablesape space warning (or any error)

I didn't change DB configuration: it is standard created with SAPINST.

Best regards,

Charlotte

Former Member
0 Kudos

Hi,

May be this sap note can help you in investigation the problem with high CPU usage: https://service.sap.com/sap/support/notes/712624