on 2023 Nov 02 2:54 PM
If I want scheduling to consider setup group between two orders, do I need to add the setup group in first operation of both the orders? or can I add them to any operation of the orders? for example can I do below?
Order 1:
op 0010 - setup group "Green"
op 0020 - blank
Order 2:
op 0010 - blank
op 0020 - setup group "Green"
or it should always be like below?
Order 1:
op 0010 - setup group "Green"
op 0020 - blank
Order 2:
op 0010 - setup group "Green"
op 0020 - blank
Request clarification before answering.
any help is appreciated