on 2025 Mar 17 11:41 AM
Hi Guys,
It is possible to settle a process order into material (production variance) with REL status. Our client has no WIP policy but prefers not to manage the TECO status.
When attempting to settle a process order in REL status, the system encountered error KD258: "Final delivery not entered for the order; it is not technically completed. How can we enable settlement into material (production variance) for orders in REL or TECO status?
Thanks for your valuable response.
Request clarification before answering.