on 2024 Jul 24 3:56 PM
Dear Experts,
Please note that we are using planning strategies 81 and 82 (related to Assembly processing) for few of our scenarios.
We observed that system is considering In-house production time and GR processing time for Sales Order scheduling.
As per our customer requirement, can you please check and let us know of any controls/configuration to consider the Total replenishment lead time for sales order scheduling.
Looking for your early feedback.
P.S.: We have maintained some Total replenishment lead time in MRP3 of Material Master.
Thanks and Regards,
Kaushik Basu