Set Lock Indicator for Activity Type

tarakesh_esarla
Participant
0 Kudos
503

Hello Guru's,

In My Current project, There had been a numerous transactions happened with few Specific Activity Types, I wanted to know what may happen if i lock the activity types.

Regards,

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

HI,

if you set the lock indicator in activity type master check F1-help for the field, its only affecting planning activities:

Lock Indicator

Indicator determining whether an activity type is locked for activit

input planning.

If the indicator is active, the affected activity type cannot be

included.

Notes

If planning is reconciled, meaning plan activity = scheduled activit

the indicator should be activated so that the plan quantity remains

unchanged.

If the indicator is inactive, the activity type can be drawn upon fo

activity input planning and indirect activity allocation in plan.

If active, the lock indicator has no effect on

o actual postings

o planning, other than activity input planning and indirect activity

allocation in plan

o activity price changes

Best regards, Christian