cancel
Showing results for 
Search instead for 
Did you mean: 

Seasonal Maintenance strategy

IlyasAhmadi
Newcomer
0 Kudos
233

Hello,

I have this requirement to have a monthly call from the maintenace plan from May till October and a 3 monthly call from November till June. 

Is it possible to achieve this by using the SAP maintenance strategies?

Could someone please help me on this?

Many thanks,

Regards,

Ilyas

View Entire Topic
preetirai1984
Participant
0 Kudos

Hi,

 

By using multiple counter plan you can achieve your requirements. In this case there will be one plan and inside that two set.

Regards,

Preeti

matjazmoser
Active Participant
0 Kudos
Greetings. I believe that in a multiple counter plan only one dimension can be time based (error message IP493).)