Hello experts,

I am facing a problem, we use a term type with Z in my company's system, like ZP, why are the term lines closed, how can I open this? Because I have a sales order of 100 units and confirmed quantity is 100, after I open delivery for 50 units then I cannot open delivery for the remaining 50 units because my confirmed quantity drops to 50.

Here an example, I create a delivery of total 70 pcs and my confirmed quantity dropped 70 and I cant create a delivery for remain 30 pcs. The add line button doesn't work by the way. How can I fix that?

Accepted Solutions (0)

Answers (2)

Answers (2)

Lakshmipathi
SAP Champion
SAP Champion
0 Kudos

I could see a Purchase Requisition from your screen shot which means, there should be a PO for the same material. Check what quantity is confirmed there and by what date

nedimyilmaz
Explorer
0 Kudos

There is an inter-company process here. PO quantity formed as much as the amount of which my pick quantity. The code has been written for this. So PR amount is 100 but PO amount is variable. I can use this PR for several times

urb
Active Participant
0 Kudos

Hello nedimyilmaz,

can you please try to create delivery in VL01N with selection date to 08.09, maybe there is some problems with availability of material in stock - is that possible?

nedimyilmaz
Explorer
0 Kudos

It doesnt work even though I give it one year later.

urb
Active Participant
0 Kudos

Hello Nedim,

Ok, but what error did you received?

nedimyilmaz
Explorer
0 Kudos

Hey,

Here the error. Because my confirmed quantity dropped and need more conf. quantity for get a delivery but I cant increase the conf. quantity anymore.