on 2011 Jul 14 6:39 AM
I've done the following-
Created new a/c group--ZNSH (ship to party) by copying standard 0002
Created a ship-to-party master record (internal) using Tcode XD01
Details--- Customer No. 20 (Name-ABCD), CoCd-SU00(Surya Enterprises)
Created partner function - ZA(Quality Inspector) by copying standard FA
Created partner determination procedure-ZNSH and maintained partner function-ZA
Created new vendor a/c group --ZZ05 by copying standard 0005
Assigned partner function-ZA to a/c group ZZ05
(IMGMMPurchasingPartner Det Define permissible
partner roles for a/c group--select new entries_
Created no.range for vendor-S1 (internal)
Assigned no.range S1 to ZZ05
Created new vendor account using V-11 Tcode
Details---Vendor No. 50 (Name-ABC), CoCd-SU00
Now, when I open the ship to party master record-20 using XD02 Tcode
and maintain partner function ZA and the number 50, and try to save it
gives an error "customer 50 has not been created"
I tried the following--
When I select from the drop down options for customer-20 from XD02, I
don't see the customer ABC
I checked FKO3, the customer 50 is there.
Please help me solve the problem.
Hi
You will not be able to assign the vendor in partner functions of customer.
As suggested above create one more customer(vendor 50) and assign it to customer master 20.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
As far my understanding , only customer related Partner Fns can be assigned in Customer Master.
In this case , Create one more customer master data and assign your vendor no :50 in it .then , you assign this new customer master in Cus.mas.partner Fns.
Regards
S.Siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
You created New partner Function ZA and check the what is the Partner type is assigned to that ZA like KU or LI
if It is KU you need to create Customer master and do the necessary configuration partner determination procedure - SD Side
If it is LI , you need to create Vendor master and do the necessary configuration partner determination procedure - MM side
then assigned to the customer system will accept
Check and revert
Regards,
Prasanna
User | Count |
---|---|
92 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.