on 2011 Dec 22 5:26 AM
Dear All,
Can Anybody explain different types of Scheduling types which are used in sap pm orders?And what are its affects on the order?
1) Forwards
2)Backwards
3)only capacity requirements
4)current date
5)Forwards in time
6)Backward in time.
Regards,
Bhanu
Request clarification before answering.
Hi,
Forward scheduling
When you set this indicator, the system schedules:
Orders forwards, based on the basic start date
Collective orders forwards, based on the specified outline start date
Networks forwards, based on the specified basic start date, and then backwards, based on the scheduled finish date or on the specified basic finish date
Backward scheduling
If you set this indicator the system schedules
orders backwards starting from the basic finish date
collective orders backwards starting from the framework finish date,
networks backwards starting from the specified basic finish date, then forwards starting from the scheduled start date or the basic start date specified.
Only calculate capacity requirements
Specifies that the system only calculates capacity requirements.
Use
In production orders, the system calculates the scheduled start and finish of the order by deducting the float before and after production from the basic order dates (order start and order finish). The calculated dates are written into all operations in the order.
In networks, the system writes the basic dates from the network header into all activities in the network.
If you use this scheduling type, the dates of all the operations/ activities are identical.
The capacity requirements are distributed across the period between the scheduled start and the scheduled finish.
Costing calculates no capacity requirements when this scheduling type is used.
Schedule from current date
If you set this indicator the system schedules
orders und collective orders forward, starting at today's date
networks backwards, starting at the basic finish date, and then forwards, starting at today's date.
Foward/Backwards in time:
Basic dates with time of day
You use this indicator to determine for process orders and production orders that when you enter the basic dates, you can also enter the time.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Scheduling types "Forwards" and "forwards in time" are generaly used for PM orders.
scheduling are done based on duration/work which we enter in the operations
Example:
Basic start date: 01.12.2011
Basic end date: 01.12.2011
if you enter 48 hours in duration field ,basic end date will change to 03.12.2011
You can use the transaction code OPU7 to configure the required scheduling types for PM orders
Regards
Seenu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
125 | |
10 | |
8 | |
5 | |
4 | |
4 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.