Scheduling time planned order

0 Kudos
304

Hi experts,

I have a question regarding the production times for my planned order.
Shouldnt the time be a lot shorter? As we have the No. Ind. Capacities at 6?
Shouldnt it be devided by 6?

Workcenter:

Scheduling

Accepted Solutions (1)

Accepted Solutions (1)

krishna_chandra5
Active Contributor

Hi wolfgangostyn,

The splits (no. of capacities) will be considered in the scheduling only if it is maintained as part of the scheduling formula (in WC) and also "Splitting required" checkbox is ticked in that specific operation detail of routing.

If you couldn't understand the system behavior after maintaining the above settings, then please share your WC scheduling formulas, routing base quantity, and planned order quantity. Then only it will be possible to analyze your case.

Regards,

Krishna Chandra