on 2021 Nov 15 7:19 PM
Hi All,
I have created Scheduling agreement with LP.
MRP run schedule lines generated & seen in ME38 .It has multiple schedule lines . I have created output LPET .but when i see the output it displays all the schedule lines with dates & qty.
Now i want to manually release the individual schedule lines one by one to the supplier as an when i want.
I am not using FRC or JIT
Please guide how to achieve this?
Request clarification before answering.
Hello,
Schedule lines do not have 'release' statuses that can be maintained by the user.
If you want to manually release the schedule lines as and when you want, you can have the MRP create purchase requisitions (possibly assigned to your scheduling agreement), and then convert individual purchase requisitions into schedule lines as and when you want (and then produce your LPET output). In order to create PRs that are automatically assigned to your scheduling agreeement, set the MRP indicator in the source list item to 1 (rather than to 2).
Regards
Gianmarco
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
39 | |
6 | |
5 | |
5 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.