on 2008 Mar 19 12:24 PM
Hi all ,
I have FG contains SFG1 , SFG1 contains SFG2 .
I am doing backward scheduling .
after MRP , in MD04 the planned order dates and time r as follows :
For FG : date time
Order finish : 30.03.2008 17:30:00
Order start : 25.03.2008 12:50:00
and for SFG1 :is in BOm of FG and seperate routing
: date time
Order finish : 25.03.2008 17:30:00 --> "this time is my problem "
Order start : 20.03.2008 10:00:00
why the ORDER finish TIME of SFG1 is 17:30:00 why it is not Order start time of FG.
Pl explain . whether it has to be happen like same above or we can make it to our rquirement... .
Regards
Hi Venky,
Please check with production finish date of SF1 Planned order.
is it also 25.03.2008 ..
please comeback
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear ,
You can not change the time to 17:30 production order as it is gryed out.
You need to deal with Lead time scheduling.
U must be assinged any scheduling margine key with order open period and Float before production etc.
Did you fine tune that option for your FG start Time with SFG Order finish time so that it should match ?
Let me know are u keeping any
1.GR processing time
2.Loading Time
3.Pick pack time
before you start FG PO
Regards
Jia
Please let us know.
Regards
Jia
User | Count |
---|---|
88 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.