Hi Experts,
I need your help, I don't understand why the result of the scheduling in IP10 is wrong. As you can see for this Mce plan I have a start of cycle = 01.01.2023 and Scheduling Period = 6 Months BUT in the IP10 (screen on the right) the end date is until 24.06.2024 it should be until 06.2023.
Please do you know from where the issue is coming?
Thank you,
Regards,