on 2008 Sep 06 1:51 PM
Dear Expert,
I need Planned order start date always at period start and delivery
date (order finish) at period end for example :
Period start 01/12/2008 and end at 05/12/2008 according to planning
calendar
Requirment date = 01/12/2008
planned order start should be = 01/12/2008 and finish date =05/12/2008
so i work with the Scheduling indicator in transaction OMI4 :
Scheduling (T439A-TERBV) to '4'
Inter.of events (T439A-INTKA) to ' '
but the result of running mrp in transaction MD04 Start date of the
planned order in not always at the Period start and also all the planned order with EM 30:
Plan process according to schedule
Thanks for your patient
Best Regards
Rami Abd El Fattah Mohamed,PPQM Functional & Technical Application
Consultant
Request clarification before answering.
Dear,
Please let us know what is the lotsize key in MRP1 you are using?
Hence you check in OMI4..for a lotsize key where the scheduling field value = 3 (Period start := start and period end := delivery date).
If not there create a new one copying from MB(monthly lot size)...just change sheduling field value from 1 to 3...save and use this new lot size key and run MRP ...you will get the result.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
61 | |
9 | |
8 | |
6 | |
5 | |
4 | |
4 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.