Scheduling agreement going for release while updating Schedule line in ME38

SAPSupport
Employee
Employee
0 Kudos

In OLA Scheduling agreement going activated flexible workflow where approval matrix same as purchase order also customization same .

Few SA going for approval when SCM Buyer updating Scheduling Line based on production demand this is abnormal behavior in Scheduling agreement flexi workflow functionality.


------------------------------------------------------------------------------------------------------------------------------------------------
Learn more about the SAP Support user and program here.

Accepted Solutions (1)

Accepted Solutions (1)

SAPSupport
Employee
Employee

What you are describing is a standard function in the ECC / System backend;

> If the buyer alters the existing SA to over / above the specified amount used in the original entry, this needs to be approved again above the released qty / amount - if goods are already scheduled, increasing the amounts to be ordered will require a re-approval and, in some cases, redistribution altogether of the overall qtys ordered, unless you specifically code the system to ignore the re-release (which is not recommended).

> If the requirement is to allow the buyers to significantly amend the SA while it is already underway, (and also ignore the criteria for a re-release) you or your ABAPers can code the User Exit outlined in this blog post (which explains the concept also)

https://blogs.sap.com/2021/07/30/release-strategy-reset-when-change-made-to-delivery-schedule/

Hope this helps!