Schedule OverView (Capacity Planning) Reddening, even though there is no overlap

SI_y_Ito
Explorer
0 Likes
421

Hi.

I dont Understand... 

Reddening, even though there is no overlap

SI_y_Ito_0-1737011319725.png

Why is this?

What are the possible causes?

please tell me…

Accepted Solutions (1)

Accepted Solutions (1)

Chuma
Active Contributor
0 Likes

Hello @SI_y_Ito 

The red highlighting in the Gantt/resource view not only shows an overlap of bars but also usually indicates a capacity conflict, for instance, when the assigned work exceeds the resource’s available hours according to its work calendar, or when there is an overlap at a more detailed level, an hourly view that isn’t visible in the weekly zoom.

I recommend checking the resource utilisation view, verifying the work calendar, and zooming in on a daily/hourly level to see where the overload occurs. Other assignments from outside your current filter can also cause the same effect.

Useful: SAP Help Portal – Resource Scheduling in S/4HANA Cloud