Schedule line generated despite delivery completed indicator.

rjha2
Newcomer
0 Likes
357

in a scheduling agreement, scheduling line has automatically been generated even though delivery completion indication is set. Is this normal behavior? line has been generated through MRP run.

Accepted Solutions (0)

Answers (1)

Answers (1)

Vaibhav-Mishra
Contributor
0 Likes

Hello rjha2,

DC indicator is set means further delivery is not expected but still Schedule lines can be triggered and GR can be posted.

So its a normal behaviour.