in a scheduling agreement, scheduling line has automatically been generated even though delivery completion indication is set. Is this normal behavior? line has been generated through MRP run.
Request clarification before answering.
Hello rjha2,
DC indicator is set means further delivery is not expected but still Schedule lines can be triggered and GR can be posted.
So its a normal behaviour.