on 2006 Aug 20 5:25 AM
Hi
How can I schedule a job to run on the last day of every month ?
I created a job using SM36. Under "Start condition" I selected start date(31st) and time and set as a "period job" (monthly job).
However, realised that after month of feb(28 days), the following month (march)'s job started on the 28th instead of the last day of the month (ie31st March).
Hope someone can advise.
Thank you.
Hi Hui,
create a job with the following start-condition:
<a href="http://help.sap.com/saphelp_47x200/helpdata/en/20/2d513897110872e10000009b38f889/frameset.htm">Job Start Management</a> - Workday/Time (>>)
choose factory calenadar AM - if available
otherwise create your own factory - calcendar and define special rules
http://help.sap.com/saphelp_47x200/helpdata/en/dd/560fdd545a11d1a7020000e829fd11/frameset.htm
Andreas
pls reward useful answers
thank you !
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.