We have created scheduling agreement with 10000 no of Qty. and w.r.t this we have maintain source list and quota arrangement accordingly.

when we run the MRP through MD02; MRP will generate scheduling lines but there is no check for target quantity of that scheduling agreement.

MRP still create scheduling line even after target qty. of SA has exceeded because of this inconsistency has been occurred in system with Schedule Qty. more than Target Qty.

is there any process which controls the above inconsistency ?

are we able to restrict scheduling line through MRP is there any control to check target Qty.?

Regards

Ganesh VU.

Accepted Solutions (0)

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Navigate to SPRO > Purchasing > Environment Data > Define Attributes of System Messages. There select 06 067 and see whether any value is set. If not, maintain "E" and retry the process. Not sure on this as long time back, I did it for similar requirement