schedule agreement delivery date vs good receipt

0 Kudos

Hi

Please help for below issue.

We are using schedule agreement for procurement process. in schedule agreement we maintained delivery date & qty through ME38.

Example :

Mateial XXXXXX create SA of 100 qty & delivery qty & date maintained as below

Date Qty

23.10.2018 -25

27.10.2018 - 25

02.11.2018-25

06.11.2018-25

on above delivery date & qty maintained in SA on that basis good receipt as below

Date Qty

25.10.2018 -25

02.11.2018 - 25

07.11.2018-25

15.11.2018-25

the requirement is how to tracking schedule delivery date & qty against goods receipt date & qty on that basis vendor performance also check

any standard report available or any logic for Z report

Maruti kulkarni

Accepted Solutions (0)

Answers (1)

Answers (1)

anilmalhotra88
Participant
0 Kudos

Hi Maruti,

In SAP you cannot get a direct link between the GRN posted & the schedule line number.You can develop your own query or abap report based on EKET & EKBE tables, the quantity & date of GRN can be distributed to schedule lines on a FIFO basis.

Regards,

Anil Malhotra