on 2011 Feb 24 3:42 PM
Hi experts:
We plan product-costing for materials in stock and product-costing in the sales order position level. The main material (FERT) is a configured material but it uses structures that are in the stock regardless the sales order. Would it be possible to calculate the product-costing in the sales orden position level but saving in the master data a product-costing for lower positions.
Example:
FERT1
ROH 1.1
HALB 1.2
ROH 1.2.1
HALB1.3
We would need to save a sales order product-cositng for FERT1 but saving a product-costing in material master for materials HALB 1.2 and HALB 1.3.
Thanks in advance
Best regards
Jose
Hi Jose
There is no way you can update Sales Order costing in the material master...
CK11N costing updates MBEW table and Sales order costing updates EBEW table...
Br, Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
112 | |
8 | |
6 | |
6 | |
6 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.